Do you need an SPCC plan?
If your shop, plant or yard stores oil, diesel, hydraulic fluid or used oil, there is a federal line at 1,320 gallons. Most places that cross it don't know they did. Six questions will tell you where you stand.
It is about how much your containers can hold, not how full they are today.
Add up the capacity of every container that holds 55 gallons or more. Drums, totes, tanks, generators and hydraulic reservoirs all count.
Completely buried tanks are counted separately, and the bar is much higher.
A ditch, storm drain or creek that a spill could reach is enough. Your dikes and berms don't count when you answer this one.
One 1,000-gallon diesel tank, four 55-gallon drums of hydraulic oil and a 275-gallon used oil tote is 1,495 gallons. That shop needs a plan.
Answer what you can. "Not sure" is a fine answer.
1. Total aboveground oil capacity, counting only containers of 55 gallons or more
Capacity, not what's in them today.
2. Completely buried tanks totaling more than 42,000 gallons?
3. If a tank failed, could oil reach a ditch, storm drain, creek or pond?
Answer as if your containment walls weren't there.
4. Any single aboveground container larger than 5,000 gallons?
5. In the last three years, has oil from your site reached water?
One spill over 1,000 gallons, or two over 42 gallons each within twelve months.
6. Do you have an SPCC plan today?
Your result shows here as you go.
This is a screening tool based on 40 CFR Part 112. It is not a regulatory determination. A few exemptions and special cases aren't covered here.
| Your facility | Plan type | Who certifies it |
|---|---|---|
| 10,000 gallons or less, no container over 5,000, clean spill history | Tier I. A shorter plan on EPA's template. | The owner or operator |
| 10,000 gallons or less, with a container over 5,000, clean spill history | Tier II. A full plan. | The owner or operator |
| Over 10,000 gallons, or a spill history that rules out the tiers above | Full plan | A licensed Professional Engineer |
The plan has to be reviewed at least every five years, and amended whenever you add a tank, move one, or change what is in it.
No. It stays at your facility. An inspector will ask to see it.
Yes. The rule counts what a container can hold.
Not by default. If a spill could get out a door or down a floor drain to a storm sewer, the rule can still apply.
We walk the site, build the oil inventory, check your containment, write the plan and train your people on it. We tell you up front which kind of plan you need and whether an engineer has to sign it.